X-ray and AOI inspection screen showing a printed circuit board under measurement
A factory acceptance test is a measurement record, not a walkaround on shipping day.

A cleaning machine that passes inspection at the factory and then underperforms on your line failed one thing first: nobody wrote down what “passing” meant. Define the factory acceptance test before the purchase order is signed, and the machine arrives with a record you can re-measure on your own floor.

CHUANGQI runs four acceptance stages on every machine before it ships: a spray-pressure and leak calibration, a temperature-uniformity check across the drying zone, a continuous run of 72 hours, and a cleanliness check on a test coupon. The list below is the one we send to buyers who ask what arrives with the machine, and the wording comes from that pre-shipment protocol.

Key takeaways

Factory Acceptance Test vs Site Acceptance Test: Two Different Risks

This article covers the machine-level acceptance test a buyer runs at the supplier’s factory before shipment, and the site test that follows installation. It is written for the procurement or process engineer who signs the acceptance page. The worked example is CHUANGQI’s own pre-shipment protocol for PCBA cleaning machines. No external test threshold is quoted here, because an acceptance number belongs to your product class and your customer requirement.

The factory test removes build risk. The site test removes installation risk. They answer different questions, and one does not cover the other.

QuestionFactory acceptance testSite acceptance test
Where it runsAt the machine builder, before cratingOn your floor, after installation
What it provesThe machine was assembled and wired to specification and the utilities behaveThe machine performs on your boards, with your chemistry and your plant air and water
What it cannot provePerformance on a board family the builder has never runWhether the cause is a build fault or a process setting
Evidence you keepPressure and leak records, temperature uniformity log, long-run log, cleanliness test resultFirst-article results on production boards, plus the acceptance route agreed with your customer

Source: CHUANGQI pre-shipment acceptance protocol for cleaning machines, 2026-10. The comparison describes which risk each test covers, not a pass value for any machine.

What to Write Into the Purchase Order Before the Machine Is Built

A specification that lists only dimensions and voltages is a purchase, not an acceptance plan. Each line below turns into a measurement your supplier has to record, and each one exists because we have seen a shipment become arguable without it.

One limitation belongs on that list, stated plainly. A factory test cannot confirm how the machine will behave on a board family nobody has run through it yet. If your product mix changes every month, the factory test proves the machine was built correctly; it does not prove your process window, and it does not replace a sample run on your own assemblies.

The Four Stages CHUANGQI Runs Before a Machine Ships

These four stages are recorded on every machine we build, and each one closes a different failure path. The order matters: a leak test taken after a long run tells you something a leak test taken before it does not.

StageWhat it removesRecord you receive
Spray pressure and leak calibrationLiquid that never arrives at the surfaces the process is meant to wetPressure reading per circuit, leak check result
Temperature uniformity in the drying zoneWet pockets that push residue back across a board after rinsingTemperature map taken across the drying tunnel
Continuous run of 72 hoursFaults that only show up after warm-up, not in the first hour of a demoRun log with every stoppage marked
Cleanliness check on a test couponA rinse stage that underperforms before the machine leaves the workshopCoupon extraction result taken before crating

Source: CHUANGQI acceptance protocol for cleaning machines, 2026-10. Every unit leaves the workshop with four records: spray pressure and leak calibration, a temperature-uniformity log for the drying tunnel, a 72-hour run log, and an extraction result from a test coupon. Tolerance values are read from that machine’s own specification sheet.

Quality engineer inspecting a populated PCBA panel at an inspection station
The record is written in the workshop; the judgement is made again on your own boards.

Limits of applicability. This checklist covers machine-level acceptance for a cleaning machine bought as a discrete unit, and it is not suitable as the only acceptance route when your customer applies a cleanliness requirement of its own: those criteria stay with your customer, and a machine record cannot stand in for a first-article run on production boards. It also assumes the cleaning step is a separate purchase; where the washer is folded into a larger line, the acceptance milestones belong in that line’s schedule instead. A stock machine can complete the four stages in a shorter window, but the record still has to exist. Skipping it saves administration and returns later as an argument.

Two other pieces on this site sit beside this one. If you would rather prove a machine on your own boards before ordering, the sample cleaning test route sends back a record measured on your assemblies before and after the wash. If the order paperwork and shipping terms are the part that is new to you, importing SMT cleaning machines walks through that side. The platform we most often write acceptance records against is the inline PCBA water cleaning machine CQ-C9610.

Engineer reviewing control parameters on a machine panel in a production hall
A criterion you can re-measure survives a change of engineer; a signature does not.

Frequently asked questions

What is a factory acceptance test for a cleaning machine?

It is a set of measurements recorded at the builder’s plant before the machine is crated, against criteria you defined in the purchase order. Typical items are a pressure-and-leak check on the spray circuits, a temperature map across the drying zone, a long continuous run, and a cleanliness reading taken from a test coupon. The value sits in the record: a machine that arrives with measurements can be measured again, and a machine that arrives with a signature cannot.

Do we have to be present at the factory acceptance test?

Attendance gives you the logs first-hand, and remote works if the protocol is written down. If you attend, bring your pass criteria and ask for raw logs rather than a finished summary. If you cannot travel, agree in advance on which records will be produced, who signs them, and how a retest is triggered. Spoken agreements are the part that does not survive a change of engineer on either side.

Can we skip the factory acceptance test for a stock model?

You can shorten it, not delete it. A machine built to a design already in production still has to be wired, plumbed and calibrated, and those are the steps where a build fault hides. The four stages above still run on a stock machine; what changes is the schedule, not the need for a record.

What happens if the machine fails a stage?

Fix it and re-run that stage, and keep both results in the file. A recorded failure followed by a passing retest tells your quality team more than a clean sheet with no history, because it shows the supplier noticed and corrected something. If the same stage fails twice on one design, treat it as a design question rather than an assembly question, and raise it before crating rather than after installation.

Next step: send the board envelope, the flux class and the boards per hour you need to hold, and we will return the acceptance items that apply to that configuration with a quote within 24 hours — request a machine acceptance plan.

About the author

Anne is an Application Engineer at CHUANGQI. She works with EMS and OEM manufacturers on cleaning-process questions: analysing flux and residue findings, sizing the right machine configuration (inline or batch, stencil, nozzle or dry ice), and supporting remote commissioning, acceptance testing and process documentation.

Have a cleaning case you want assessed? Send us the board, flux and volume data →